Planning application HS/FA/26/00521 · Conditions, certificates and amendments

Variation of Condition 2 (approved plans) and Condition 9 (joinery details) of Planning Approval HS/FA/25/00340…

1 St Matthews Road, St Leonards-on-sea

This asks to change the conditions of a permission already granted.

  1. ReceivedTue 8 Sep 2026
  2. ValidatedWed 9 Sep 2026
  3. Out for commentSite notice posted 23 Sep
  4. DecisionGranted permission, week of Mon 2 Nov 2026

What is proposed

In the council’s words, from its weekly list:

Variation of Condition 2 (approved plans) and Condition 9 (joinery details) of Planning Approval HS/FA/25/00340. Amendment - Removal of French doors in South East (rear) elevation and replace with ground floor window, removal of ground floor window in South West (side) elevation and replace with French doors.

Where it stands

The council’s file ↗

Conditions attached

The decision notice on the council’s file (published Tue 3 Nov 2026) attaches 18 conditions. In the council’s words, each with the reason it gives:

  1. Time limit to start
    The development hereby permitted shall commence before the expiration of the time limit imposed on application ref: HS/FA/23/00722.

    Reason: This condition is imposed in accordance with the provisions of Section 91 of the Town and Country Planning Act 1990.

  2. Built to the approved plans
    The development hereby permitted shall be carried out in accordance with the following approved plans: BA2356.01, 5044.1D, 5044.3A, 5044.8E, 6134 Sheet 01 (Drainage layout drawing), 6134 Sheet 02 (Drainage details drawing - 1 of 2), 6134 Sheet 3 (Drainage details drawing - 2 of 2), 5044.10A, 5044.11A, 5044.12, 5044.9, 5044.CMP, GCL + EDU DRAFT2

    Reason: For the avoidance of doubt and in the interests of proper planning.

  3. Hours of building work
    With the exception of internal works the building, the works required to carry out the development allowed by this permission must only be carried out within the following times:- 08.00 - 18.00 Monday to Friday 08.00 - 13.00 on Saturdays No working on Sundays or Public Holidays.

    Reason: To safeguard the amenity of adjoining residents.

  4. Construction management
    The construction of the development shall be carried out in accordance with the procedures detailed in the Construction Method Statement (Amended 03.05.2025), as prepared by Michael D Hall Building Design Services Ltd and associated Construction Management Plan (drawing ref: 5044.CMP), and the measures shall be maintained throughout the construction period.

    Reason: To protect the amenity of surrounding occupiers and to safeguard highway safety.

  5. Drainage and flooding
    (i) The construction of the development shall be carried out in accordance with the foul and surface water drainage strategy as detailed in drainage layout drawing ref: 6134 Sheet 01, drainage details drawing 1 of 2 (ref: 6134 Sheet 02) and drainage details drawing 2 of 2 (ref: 6134 Sheet 03). (ii) The development shall then be carried out in accordance with the details approved under (i) and the dwelling hereby approved shall not be used until those works have been completed; and (iii) Prior to the occupation of the new dwelling, evidence that demonstrates that the necessary drainage infrastructure capacity is now available to adequately service the development shall be submitted to and approved in writing by the Local Planning Authority. Once installed, the drainage systems shall be maintained in good working order in accordance with the Operation, Management and Maintenance Plan prepared by RSPD Drainage Consultants (July 2025, Job No 6134 Rev 0).

    Reason: In order to secure a well-planned development that functions properly and in order to prevent increased risk of flooding.

  6. Bins and recycling
    The development shall not be occupied until a refuse store has been provided within the site in accordance with details provided on plan ref: 5044.8E. Once installed, the refuse storage facilities shall thereafter be retained within the site for that sole purpose.

    Reason: In order to secure a well planned development.

  7. Parking, access and cycles
    The development shall not be occupied until secure cycle storage facilities for at least 2 bicycles have been provided within the site in accordance with the details on plan ref: 5044.8E. Once installed, the cycle storage facilities shall hereafter be retained and they shall not be used for any other purpose other than for the parking of bicycles.

    Reason: In order that the development site is accessible by non car modes and to meet the objectives of sustainable development.

  8. Trees and landscaping
    The hard and soft landscaping works shall be carried out in accordance with approved plan 5044.8E and the works shall be completed prior to the first use of the new dwelling in accordance with the approved details and maintained thereafter.

    Reason: In the interests of the visual amenity.

  9. Materials and design details
    The construction of the joinery to the new dwelling, the pedestrian gate and gate piers shall be carried out in accordance with the details shown in plans ref: 5044.9, 5044.10A, 5044.11A, 5044.12, and GCL + EDU DRAFT 2.

    Reason: In the interests of visual amenity and in order to conserve and enhance the Conservation Area setting.

  10. Trees and landscaping
    The external finishing materials to be used in the construction of the new dwelling and hard landscaping works shall be in accordance with the materials detailed in the External Materials Schedule prepared by Michael D Hall Building Design Services Ltd and the development shall be completed in accordance with the approved schedule and maintained thereafter.

    Reason: In the interests of visual amenity and in order to conserve and enhance the Conservation Area setting.

  11. Noise, plant and smells
    Prior to the installation of the Air Source Heat Pump, an acoustic report shall be submitted to and approved in writing by the Local Planning Authority. This report shall outline that the rating level from ASHP, which should not exceed recommended noise levels. The air source heat pump shall be installed in accordance with the approved details. Further advice is provided in the Heat Pumps Professional Advice Note 2022: heat-pumps-briefing-note-professional-advice-note.pdf (cieh.org)

    Reason: In the interest of neighbouring amenity.

  12. Permitted development rights removed
    Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015 (or any order revoking and re-enacting that Order, with or without modification) no extensions, windows or outbuildings permitted under classes A, B, C or E shall be added to the residential development hereby approved other than those expressly authorised by this permission.

    Reason: In the interests of visual amenity and neighbouring amenity.

  13. Parking, access and cycles
    The development shall not be occupied until a parking area and vehicle turning area have been provided within the site in accordance with plan ref: 5044.8E. Once constructed, the areas shall thereafter be retained and they shall not be used for any other purpose other than for the parking and turning of motor vehicles. The proposed parking spaces shall measure at least 2.5m by 5m in size (with an additional 0.5m to be added where spaces abut walls or fences).

    Reason: In order to ensure safe access to the site and to avoid congestion on the highway.

  14. Something else
    The development shall be undertaken wholly in accordance with the details set out in the approved waste minimisation statement.

    Reason: To minimise the amount of construction and demolition waste being disposed of in landfill sites in accordance with the East Sussex County Council Supplementary Planning Document on Construction and Demolition Waste.

  15. Trees and landscaping
    (i) Tree planting works shall be undertaken in accordance with approved plan 5044.8E. All tree planting shall be carried out in accordance with the approved details and in line with the agreed timetable. (ii) All trees produced abroad but purchased for transplanting shall spend at least one full growing season on a UK nursery and be subjected to a pest and disease control programme. Evidence of this control programme, together with an audit trail of when imported trees where needed and their origin and how long they have been in the nursery, will be supplied to the Local Planning Authority prior to the commencement of any tree planting; and (iii) If, within a period of five years from the date of the planting of any tree, that tree, or any tree planted in replacement of it, is removed, uprooted or destroyed or dies, or becomes, in the opinion of the Local Planning Authority, seriously damaged or defective, another tree of the same species and size as that originally planted shall be planted in its place.

    Reason: In the interest of visual amenity.

  16. Biodiversity and ecology
    Prior to the occupation of the development, a scheme of biodiversity enhancement measures shall be submitted to the Local Planning Authority for their prior written approval. The measures shall be implemented within the site prior to occupation in accordance with the approved details and they shall be retained in perpetuity.

    Reason: In order to encourage biodiversity.

  17. Parking, access and cycles
    Visibility splays of 2.4 metres by 43 metres shall be maintained at the entrance to the site at all times and kept free of all obstructions over a height of 600mm.

    Reason: To ensure the safety of persons and vehicles entering and leaving the access and proceeding along the highway.

  18. Parking, access and cycles
    Prior to their installation within the site, the elevational details for the combined cycle store/shed and refuse store shall be submitted to and approved in writing by the Local Planning Authority. The stores shall be installed within the site prior to the occupation of the new dwelling in accordance with the approved details and retained thereafter.

    Reason: In the interest of visual amenity.

We copy the numbered conditions and their reasons and nothing else from the notice. Its notes to the applicant are on the file. The label on each is ours, by rules on the council’s wording. The conditions the council attaches, by kind of application

Conservation and heritage on this street

We couldn’t place St Matthews Road’s line on the map, so we can’t say whether it reaches a conservation area. The town’s conservation areas lists each one with the council’s map.

The council’s Article 4 direction on houses in multiple occupation covers the whole town (in force since 2 July 2012): turning a house into a shared house for three to six people needs planning permission. The council’s page ↗

Conservation areas, Article 4 directions and tree preservation orders: Hastings Borough Council, Open Government Licence v3.0. Street lines © OpenStreetMap contributors.

Flood zones, the coast and protected nature on this street

We place an application by the street in its address, so these are about where St Matthews Road runs. For the site’s boundary, see the application’s documents on the council’s file.

Flood zones

St Matthews Road has no line on our map, so we can’t say which flood zone it is in.

A street’s line is not an address. For a particular address, use the Environment Agency’s Check your long term flood risk ↗; for a planning site, its Flood map for planning ↗. Flood warnings in force now are on Live now.

Flood zones: © Environment Agency copyright and/or database right 2025. Open Government Licence v3.0. Read 10 November 2026.

Coastal erosion and the Shoreline Management Plan: © Environment Agency copyright and/or database right 2025. © Environment Agency copyright and/or database right 2015. Open Government Licence v3.0. Read 10 November 2026.

Protected sites: © Natural England copyright. Contains Ordnance Survey data © Crown copyright and database right 2026. Open Government Licence v3.0. Read 10 November 2026.

Street lines © OpenStreetMap contributors.

Comments on the application

The council’s file counts 2 comments from the public: 1 objection, 1 in support (as it stood on Tue 3 Nov 2026).

Is a comment public?

The council’s page on commenting says: “All comments will be made available to view online and will be treated in accordance with our privacy policy. Comments will be redacted where they contain personal information or are inappropriate in their content.” It also says: “Please note that we do not accept anonymous comments.” Commenting on an application, on the council’s site ↗ (read 13 October 2026).

We count the comments on the council’s file. We never copy a commenter’s name, address or words, and we don’t list who objected: that is on the file.

If you think work doesn’t match what was approved

The council’s planning enforcement team looks into building work or a use that may not have permission, or may not follow the approved plans or conditions. Its page explains how to report it and which cases it deals with first: planning enforcement on the council’s site ↗

Our planning record starts on 21 April 2026, from the council’s weekly lists of new and decided applications. We list the site, the proposal, the dates, the decision, the comment counts and a permission’s conditions. We don’t copy a commenter’s or an individual applicant’s details. An applicant is named only when it is an organisation we can match exactly to a council, a registered charity or a company on Companies House. The council decides planning applications. We don’t.