This report tracks progress on the savings identified for the 2026/27 budget through the PIER process, as at Period 06, September 2026. p1

Some Shared Services savings were reprofiled and deferred, rather than removed, because of the later mobilisation of the Transformation and Shared Services programme and the timing, complexity and uncertainty of Local Government Reorganisation. p2

We’ve left out 3 more sentences of this summary because they didn’t pass our check against the paper.

Show the 2 passages this is based on
  • p1Achievement of the 2026/27 PIER savings during the year - Period 06 - September 2026 Appendix 3 Savings identified during the PIER process for the 2026/27 budget supporting information set out in Budget Book Appendix K PIER Saving £ Savings achieved £ RAG Comments page 1 ↗
  • p21. Shared Services The savings profile in Appendix K reflects a reprofiling of some in-year savings in 2025/26, primarily due to the later mobilisation of the Transformation and Shared Services programme together with the timing, complexity and uncertainty associated with Local Government Reorganisation. Some of these savings have therefore been deferred rather than removed and are reflected in the revised phasing across 2026/27 and subsequent years within the Medium Term Financial Strategy. A significant amount of enabling work has been undertaken in some areas increasing the level of assurance that the savings will be achieved. Prudent assumptions have also been applied where proposals remain at an early stage of development, with further refinement to be brought forward through established governance and budget-setting processes.” £508,368 £388,539 Amber Savings have been identified through on going discussions around sharing of services and regularly reported on Shared Services and Transformation board. Savings relating to the IT and various leadership posts have been achieved at initial budget setting for 2026-27 with further savings partially achieved and agreed through progress of shared services. page 1 ↗